If 3 persons can do a piece of work in 4 days, then 4 persons can do it ____days
Answers
Answered by
0
Answer:
3 days
Step-by-step explanation:
the piece of work can be done by 4 persons in 3 days
Answered by
0
Answer:
Dear mate here is your answer.
Step-by-step explanation:
if 3 person can do a piece of work in 4 days, then 4 person can do it in 3 day
please mark me as Brainlist