if 30 men can do job in 21 days then how many days would 45 men finish the job
Answers
Answered by
6
Answer:
14 days
Step-by-step explanation:
we can see that it is inverse variation becuase when
30 can do it 21 days
then 45 would take less time
one quantity increases and other decreases
so take 30 men as x1
and 45 men as x2
take 21 days as y1
and the unknown as y2
inverse variation formula =x1/x2=y2/y1
so 30/45=y2/21
cross multiply
30*21/45
=14days
Answered by
2
Answer:
No of Mens×No of Days = constant
30×21 = 45× x
⇒x = 30×21/45
⇒x = 14
answer= 14 days
Step-by-step explanation: