If 30 men can do job in 80 days how many more men would be required to do it
in 50 days?
Answers
Answered by
1
Answer:
if 30 men took 80 days to complete the job
so,
x1 =30, x2=80
x1y1 = x2y2
x2= 50
30 x 80 = 50 x X
30 x 80/50 = X
X = 42 mens
Answered by
0
number of men be x=30
working day y=80
x proportional 1/y
therefore, x=k/y ( k is a non zero variation constant)
k= x. y
=30.80
=2400
then, x =2400/y
=2400/50
=48 men
more men require 48-30
=18 men