If 30 men complete 1/7 the work in 2 days. How many more men should join in now, if the work
has to be completed in 10 more days?
Answers
Answer:
ANS : 6
Step-by-step explanation:
Given, M1 = 30
M2 = 30 + x
W1 = 1/7
W2 = 1 - 1/7 =6/7
D1 =2 and D2 = 10
According to the formula, M1D1W2 = M2D2W1
30×2×(6/7) = (30+x)×10×(1/7)
⇒ 360 = 300 + 10x
⇒ 10x = 360-300
⇒ x = 60/10
⇒ x= 6
6 more men are required to complete the work in next 10 days.
Given,
30 Men complete 1/7 of work in 2 days
To Find,
Number of more men require to complete the work in 10 more days
Solution,
Amount of work left to do = 1 - 1/7
Amount of work left to do = 6/7
Now, let the number of more men needed to be 'x'
= Constant
Therefore, the above formula would be equal for both the cases
Case 1 -
Number of men = 30
Number of days = 2
Work done = 1/7
Case 2 -
Number of men = 30 + x
Number of days = 10
Work done = 6/7
30 * 2 * 7 =
30 * 2 * 6 = (30 + x) * 10
360 = 300 + 10x
10x = 60
x = 6
Therefore, 6 more men are required.
#SPJ2