Math, asked by ajay84652, 8 months ago

If 30 men working 7 hrs per day can finish a work in 15 days, how long will 25 men take to finish the
same work in 12 days?
(a) 8
(b) 10.5
(c) 12.5
(d) 15​

Answers

Answered by sumedhkhatode29
0

Answer:

12.5

Step-by-step explanation:

30 men – 15 days

25 men – x days

(25 × 15 )/30

375/30= 12.5