If 30 persons take 10 days to complete a certain work working 8 hours a day, then 40 persons should work how many hours a day so that the work is completed in 6 days?

Answers

Answered by dyesu
0

Answer:

40 person should work 10 hours a day so that the work is completed in 6 days .

Step-by-step explanation:

please make me as brainilist.

Answered by sagaramisha66
1

Answer:

Step-by-step explanation: