if 30 persons take 10 days to complete a certain work working 8 hours a day than 40% should work how many hours a day so that the work is completed in 60 days....solve this out guys
Answers
Answered by
17
Given:
30 persons take 10 days to complete a certain work working 8 hours a day than 40 %
To find :
how many hours a day so that the work is completed in 6 days
STEP BY STEP EXPLANATION:
30 × 8 × 10 = 40 × 6 × x
2400 = 240 X
x =
x = 10 hours
ANSWER:
∴ 40 people should work 10 hours in a day so they can complete the work at in 6 days
Hence verified !