If 30 workers can build a bridge in 120 hours, how many workers will be required to
complete the same amount of work in 90 hours?
Answers
Answered by
0
Answer:
40 workers
Step-by-step explanation:
30 workers can build a bridge in 120 hours,
let 'x' workers can build a bridge in 90 hours,
so
30 × 120 = x × 90
x = 40 workers
i hope the above solution will help you.