Math, asked by kingshukbasu828, 1 year ago

If 300 man can do a work in 16 days ,how many man can do 1/4 of the same work in 15 days

Answers

Answered by anoopsingh2
7
hope its help you dear.....
Attachments:

kingshukbasu828: 16------1-------300
kingshukbasu828: 16------1----300. 1-------1----300×16. 15-----1----(300×16)/15. 15----1/4--(300×16)/(15×4)=80