If 300 man can do a work in 16 days ,how many man can do 1/5 of the same work in 15 days
Answers
Answered by
0
now given that a work can be done by 300 men in 16 days
and given to find how many men can do Same in 15 days to complete 1/5
so the work is considered as (300/16)/5=x/15
300/80=x/15
15×300/80=x
x=56.25
so it requires 56 men to do work