Math, asked by asingh32, 10 months ago

if 32 men can do a piece of work in 45 days, then in how many days will 15 men complete the same work

Answers

Answered by samir4934
23

If 32 men complete the work in 45 days.

Then1 man complete the work in 45×32 days

So15 men can complete the work in 96 days

Answered by Riya599268
0

Answer:

96 Days

✌✌Hope it helps

Attachments:
Similar questions