If 32 men work 12 hour can finish a work in 15 days how many workers 10 hours a day can do double the worj in 24 days
Answers
Answered by
0
Answer: 48 workers can do double the work in 24 days, working 10 hours a day.
Step-by-step explanation:
Given data:
Number of men = 32
Time taken = 12 hour
Number of days = 15
Total time taken to finish the work = 12 x 15 hours = 180 hours
Therefore amount of work done = 32 x 180 = 5760
Now, if same work is to be done in 10 hours for 24 days, then
Total time taken = 10 x 24 = 240 hours
Amount of work = 5760,
∴ number of workers = = 24 workers
Now, if double work is to be done, then we will need , 24 x 2 = 48 workers.
Hence, 48 workers can do double the work in 24 days, working 10 hours a day.