If 32 men working 12 hours a day can do a work in 15 days, how many men working 10 hours a day can do double that work in 24 days?please answer fast. I will mark as brainliest ​

Answers

Answered by redhujaipal20
4

Answer:

No. of hours 32 men work in 1 day= 32 x 12=384 hours.

No. of hours 32 men work in 15 days= 384 x 15=5760 hours.

In second condition,

Work to be done is double, so number of hours required= 5760 x2= 11520 hours.

Let number of men can do double work = x

X men x 10 hours x 24 days = 11520

240 X = 11520

X = 11520/240=48 men.