If 32 men working 12 hours a day can do a work in 15 days, then how many
men working 10 hours a day can do double that work in 24 days
Answers
Answered by
4
48 men working 10 hours a day can do double that work in 24 days.
Step-by-step explanation:
We know that the formula of the Man-Days-Hours is given by,
Here we have,
M1 = No. of workers = 32
D1 = No. of days = 15 days
H1 = No. of hours a day = 12 hours
H2 = No. of hours a day = 10 hours
D2 = No. of days = 24 days
W1 & W2 = work done
M2 = No. of workers = need to find?
It is given that the work done by M2 is double the work done by M1 i.e.,
W2 = 2W1 ⇒ W2/W1 = 2/1
Therefore, by substituting the given values
⇒ M2 =
⇒ M2 = 48 days
Thus, 48 men can do double the work by working for 10 hours a day in 24 days.