if 3200 people need 160 days to complete a task then 4000 people need how many days to complete the task??
Answers
Answered by
0
Answer:
128 days
Step-by-step explanation:
3200 ---> 160
4000 ---> X
X = 3200 × 160 / 4000
X = 128 days