If 35 men can complete a work in 8 days, in how many days can 20 men complete the same work?
Answers
Answered by
0
Answer: 14 days
Mark me as brainlist
Step-by-step explanation:
35 men complete a work in= 8days
1 men complete a work in= 8*35days
20 men complete a work in=8*35/20=14 days