If 35 people do a work in 8 days then how many people do that work in 10 daysrn
Answers
Answered by
0
Answer:
28
Step-by-step explanation:
Answered by
1
35 people work = 8days
1 people work = 35*8days
in 10days no of people work = 35*8/10= 28