if 35 womens do a piece of work in 12 days how many womens are to be requires to do same work in 21 days
Answers
Answered by
1
in 12 days number of women required to complete the work is 35.
so, in 1day number of women required to complete the work will be 35×12
and in 21 days number of women required will be 35×12/21=20
therefore 20 women will be required to complete that piece of work in 21days.
so, in 1day number of women required to complete the work will be 35×12
and in 21 days number of women required will be 35×12/21=20
therefore 20 women will be required to complete that piece of work in 21days.