Math, asked by mehulumat2, 11 months ago

if 36 binders bind 900 books in 10 days how many binders will be required to bind 600 books in 12 days​

Answers

Answered by ravindraindu1980
0

Answer:

hope it is useful to you

Attachments:
Answered by Raghav1330
0

The number of binders that will be required to bind 600 books is 20.

Given:

36 binders bind 900 books in 10 days.

To Find:

The binders will be required to bind 600 books in 12 days.

Solution:

Here, it is given that 36 binders bind 900 books in 10days.

let's suppose that the binders bind 600 books in 12days is x.

now, the number of books that bind is directly proportional to the number of binders and the total number of days they worked.

so, by using the direct proportional, we will get,

\frac{900}{10\times 36}=\frac{600}{12\times x}

now, after calculating the common factors from the numerator and denominator.

we get, \frac{5}{2}=\frac{50}{x}

now,

5x=100\\x=20

Hence, the number of binders that will be required to bind 600 books is 20.