Math, asked by pandey1785, 11 months ago

If 36 boys can do a work in 14 days, how long will 28 boys take to do the same work?​

Answers

Answered by streetburner
1

Answer:

18

Step-by-step explanation:

By applying MDH/w (Man*days*hours/work) ,

36*14 = 28*D

D = 18 days .