If 36 boys can do a work in 14 days, how long will 28 boys take to do the same work?
Answers
Answered by
1
Answer:
18
Step-by-step explanation:
By applying MDH/w (Man*days*hours/work) ,
36*14 = 28*D
D = 18 days .
Similar questions
Political Science,
5 months ago
Math,
5 months ago
Physics,
11 months ago
Biology,
11 months ago
Math,
1 year ago