If 36 labourers can construct a road in 12 days how many days will it for 16 labourers to construct the same road

Answers

Answered by bson
1

Step-by-step explanation:

m1*d1=m2*d2

36*12 = 16×d2

d2= 36×12/16= 9×3=27 days

Answered by rk870310
0

Answer:

days=36*12/16=27

so the work will be finished in 27 days