If 36 labourers can construct a road in 12 days how many days will it for 16 labourers to construct the same road
Answers
Answered by
1
Step-by-step explanation:
m1*d1=m2*d2
36*12 = 16×d2
d2= 36×12/16= 9×3=27 days
Answered by
0
Answer:
days=36*12/16=27
so the work will be finished in 27 days