Math, asked by Madhan1037, 1 year ago

if 36 men can compelet work in 24 days . how many extra men be employed so as to complete the work in 18 days

Answers

Answered by dksingh86
12
it is indirect proportion
36*24=x*18
864=x*18
x=864/18
x=48