Math, asked by nitudevii3635, 10 months ago

if 36 men Can Complet a work
in 24 days
entra men
employed so as to complete the
in 18 days
How many
mark​

Answers

Answered by ojhaarun20
1

Answer:

the answer of this question will be 12