If 36 men can do a piece of work in 24 days, then 16 men will do the same work in
Answers
Answered by
7
Solution:-
36 men can do it in 24 days.
1 man can do it in 24 × 36 days.
16 men can do it in
Answer:-
54 days.
Hey mate this can help you.
Answered by
3
Answer:
54 days
Step-by-step explanation:
Given, 36 men can finish a piece of work in 24 days
=> The number of man-days = 36*24 = 864
Let x be the number of days taken by the 16 men to do the piece of work
=> The number of man-days = 16x
But the number of man-days remains constant.
=> 16x = 864
x = 864/16 = 54
=> 16 men take 54 days to complete the piece of work.