if 36 men can do a piece of work in 24 days then 16 men will do the same work in how many days?
Answers
Answered by
1
Answer:
36 men complete work in 24 days
1 men complete work in 36×24 days
16 men complete work in (36×24)/16 days
=54 days
Answered by
0
Answer:
answer is 54
Step-by-step explanation: