If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
Answers
Answered by
5
Step-by-step explanation:
36men in 25 days
1 men will do in 25×36
15 men will do in (25×36)/15=60days
just keep in mind that when no. of men increases then no. of days decreases
Answered by
0
let the no.of. days be x
so ,
36 * 25 = x * 15
⇒ x = (36*25)/15 = 12 * 5 = 60 days
Thus ,
The Required days is 60 days