If 36 men can do a piece of work in 25 days, in how many days will 15 men do the same work?
Answers
Answered by
1
Answer:
60 days.
Explanation:
Hope it helped you.
Attachments:
Answered by
0
Answer:
=> 15 men take 60 days to complete the piece of work.
Explanation:
Given, 36 men can finish a piece of work in 25 days
=> The number of man-days = 36*25 = 900
Let x be the number of days taken by the 15 men to do the piece of work
=> The number of man-days = 15x
But the number of man-days remains constant.
=> 15x = 900
x = 900/15 = 60
=> thus , 15 men take 60 days to complete the piece of work.