Math, asked by lucky1925, 20 days ago

if 36 men can do a piece of work in 25 days, in how many days will 15 men do it​

Answers

Answered by ItzAshleshaMane
5

36 men can do the work in = 25 days

36 men can do the work in = 25 daysthen, 1 men can do it in = 25 * 36 (as 1 men will take more time)

36 men can do the work in = 25 daysthen, 1 men can do it in = 25 * 36 (as 1 men will take more time)so, 15 men can do the work in = 25 * 36 / 15 = 60 days

Hope it will help you..

Answered by Cooky26
3

Answer:

See the attachment

Step-by-step explanation:

hope it helps you!

 \:

Attachments: