Math, asked by shilpasahdev, 6 months ago

If 36 men can do a piece of work in 25 days then, find the number of men required to complete the same job in 15 days?

Answers

Answered by kusumkumari7488
0

Answer:

FL of the day of the day of the time you took place on it and you

Answered by rb572945
1

Answer:

The work requires 36*25 man-days to complete. So if 15 men are to do the same work they will take 36*25 man-days/15 men = 60 days

Similar questions