if 36 men can do apiece of work in 7days,how many men will be needed to do the same work in 42 days
Answers
Answered by
0
Answer:
6 Men will be needed
Step-by-step explanation:
⇒ 7 days --------- 36 men
⇒ 1 day ----------- 36×7 men [∵ Men & Days are inversely proportional]
⇒ 42 days ------- 252/42 men
= 6 men ←ANSWER
PLEASE MARK AS THE BRAINLIEST!!!!!
Answered by
0
Answer:
6 men
Step-by-step explanation: inverse proportion:x1/x2=y2/y1
So,36/42=y2/7
x=36/42*7
x=6
Therefore,6 men will be needed to complete the work in 42 days.