# If 36 men can finish a work in 25 days ,how many days will 15 men take to do it
?
# 12 workers take 4 hrs to complete a job. How long would it take 15 workers to
complete the job?
Answers
Answered by
2
Answer:
men. days
36. 25
15 x
36×25=x×15
900=15x
x=900
_____
15
x = 60
60 days will take to complete work by 15 men
Similar questions