Math, asked by vinitagarg8532, 10 months ago

if 36 men finish a piece of work in 25 days how many days will 15 men take to do it?​

Answers

Answered by Manirudh3
0

Answer:

the answer is 15/36 ×25 = 14.15 days

Answered by LAKSHIYAARKTUTORIALS
2

Answer:

Men Days

36 25

15 no. of days = ?

it is in inverse proportion

 \frac{36}{15}  \:  =  \frac{n}{25 }  \\  \frac{36}{3}  =  \frac{n}{5}  \\ 12 =  \frac{n}{5}  \\ n = 60

hence it takes 60days