if 36 men finish a piece of work in 25 days how many days will 15 men take to do it?
Answers
Answered by
0
Answer:
the answer is 15/36 ×25 = 14.15 days
Answered by
2
Answer:
Men Days
36 25
15 no. of days = ?
it is in inverse proportion
hence it takes 60days