Math, asked by rennuballa, 1 month ago

if 36men can do piece of work in 24 days ,then 16 men will do the same work in​

Answers

Answered by madhuwailic
1

Step-by-step explanation:

If 36 men can do the work in 24 days

36 man will do 1/24 work in 1 day

1 man will do 1/36×24 work in 1 day

16 man will do. 1×16/36×24 work in 1 day

no of days 16 man will take to do the work will be

24×36/16

=54 days

Ans- 16 man will take to do the same work in 54 days