If 4/7 of a piece of work is completed in 7/4 days, in how many days can rest of the work be completed ?
(a) 7/3 days
(b)3/7 days
(c) 21/16 days
(d) 16/21 days
Answers
Answered by
7
Answer:
the rest of the work will be finished in .,..
=
answer is 21/16 days
Answered by
0
The correct option is (c) 21/16 days.
Step-by-step explanation:
Consider the provided information.
It is given that 4/7 of a piece of work is completed in 7/4 days.
This can be written as:
of work = days
Time required to complete the work is:
Work = days
Work = days
But 4/7 of a piece of work was completed. That means remaining work is 3/7.
Multiply both the sides by 3/7.
of work = days
of work = days
of work = days
Hence, rest of the work will completed in 21/6 days.
Thus, the correct option is (c) 21/16 days.