If 4 boys or 6 girls can do a work in 40 days . How many days will 4 boys and 14 girls take to do the same work.
Answers
Answered by
1
Answer:
Step-by-step explanation:
Answered by
1
Step-by-step explanation:
b1×g1×t1=b2×g2×t2
4×6×40=4×14×t2
240×4=56t2
960=56t2
t2=960/56
t2= 17.14 days
Similar questions
Math,
5 months ago
Hindi,
5 months ago
Business Studies,
11 months ago
Business Studies,
11 months ago
Biology,
1 year ago
Math,
1 year ago