if 4 man can do a piece of work in 10 days how long will it take for 5 man to do the same work
Answers
Answered by
2
Answer: 8 days
Step-by-step explanation: 4 men can do a piece of work in 10 days.
So, one man will do the same work on 10*4= 40days.
Then 5 men will do the sameness work in 40/5= 8 days.
So, 5 men will take 8 days to complete the same work.