Math, asked by athokpampibarel, 2 months ago

If 4 men can do a peice of work in 30 days , in how many days could 10 men could do the same work ?​

Answers

Answered by NewtonofINDIA
1

4 x 30 = 10 x X

X = 12 days

pls mark as brainliest

Answered by JhaNotes
0

Answer:

12

Step-by-step explanation:

4men~30days

1man~30x4 days

10men~ 120/10 days=12 days

Similar questions