Math, asked by javeeddkh, 10 months ago

if 4 men do a job in 30 days. then 10 men may do the job in how many days??​

Answers

Answered by asahilthakur
1

Answer:

Step-by-step explanation:

4 men can do a job in 30 days. This means in 1 day, 4 men will do 1/30th job. In 1 day, 1 man will do 1/120th job. This means in 1 day, 10 men will do 1/12th work. Therefore, 10 men will do the job in 12 days.