If 4 men or 6 women can do a work in 20
days, how long will 12 men and 2 women take
T
Answers
Answered by
6
Step-by-step explanation:
Let the amount of work done by 1 man in a day be m, and that done by 1 woman be w.
Now, 4m=6w
Or, w=
3
2m
………(1)
Also, amount of work done by 4 men in a day =4m
Or 4m=
42
1
Or, m=
168
1
………(2)
Using (1) and (2), amount of work done by 12 men and 3 women in a day is 12m+3w
=12m+2m (substituting w from 1)
=14m
=14/168
=1/12
So, the total work will be completed in 12 days.