Math, asked by alshifahedayet, 3 months ago

If 4 men take 27 hours to do a job. How long will 6 men take to complete the job​

Answers

Answered by ajitkrg4
0

Answer:

4men do this job=27hrs

1man do this job=27/4

6men complete the job=27/4×6

=81/2

Answered by IntelligentAshish
0

Answer:

18 hours

Step-by-step explanation:

1 man will complete the job in 4×27

6 men will complete the job in \frac{(4*27)}{6} = 18 hours