if 4 people can do a piece of work in 16 days working 5hours each day .in how many day will the same wory be completed by 20 people working 4hours each day​

Answers

Answered by saninkiliyamannil
0

Answer:

4*16*5/(20*4) = 4 days. The work will be done in 4 days by 20 people each working 4 hours a day.