If 4 workers finish a work in 4 days , how many days will 1 worker need to finish the same work ? SOLVE THE FOLLOWING
Answers
Answered by
1
Step-by-step explanation:
Days Workers
4 4
x 1
This is a case of inverse proportions.
So, 4×4 = 1×x
16/1 = x
16 = x
x= 16
Therefore, one worker will be able to do the same job 16 days