if 40 men build 4 buildings in 12 months how many men would be required to build 6 houses in 4 months
Answers
Answered by
4
Hope it helps u and please follow me and mark me as the brainliest
Attachments:


Answered by
2
There are 80 men required to build 6 houses in 4 months.
Step-by-step explanation:
Since we have given that
Number of men = 40
Number of buildings = 4
Number of months = 12
If the number of buildings = 6
Number of months = 4
Let the number of men be 'x'
According to question, we get that
Hence, there are 80 men required to build 6 houses in 4 months.