Math, asked by sunitachohansop15uef, 1 year ago

if 40 men can do a piece of work in 70 days in how many days will 56 men complete the same work​

Answers

Answered by syedali14
4

Answer:

let the no. of Day taken by 56 men be x

this is a case i.v.

=40×70=56×x

=40×70/56=x

=50=x

=x=50days