if 40 men can do a piece of work in 70 days in how many days will 56 men complete the same work
Answers
Answered by
4
Answer:
let the no. of Day taken by 56 men be x
this is a case i.v.
=40×70=56×x
=40×70/56=x
=50=x
=x=50days