Math, asked by khalilbuttkhalilbutt, 10 months ago

If 40 workers do a work in 35 day in how many day will the same work be done by increasing 10 more
worker

Answers

Answered by Anonymous
7

Hey,your answer is 28 days.

Hope this helps you a lot...