If 42 men working together can construct a road in 13 days how long will take to 39 men construct the road ??
Answers
Case 1 :
Men = 42
Time taken = 13days
Case 2 :
Men = 39
Time taken = x
➺ How long will it take if 39men construct the road= ?
As in inverse proportions we know that
Hence the road will get constructed in 14days
Answer:
- 14 days
Step-by-step explanation:
Let required number of day is x
Clearly, the lesser number of men , number of days are in constant.
So , it is a case of inverse variation.
Now, According to the information
⟼ 42 × 13 = 39 × x
⟼ 42 × 13 = 39x
⟼ 42 × 13 / 39 = x
⟼ 14 = x
Thus, 39 Men construct road in 14 days. Ans.
Note→ Stay connected with the attachment.
_______________________________________________________________
♦ Extra Information
In case of inverse variation on increase in one quantity result decrease in the other quantity and vice- versa.
If the value of two quantities depend upon each other in such a way that are change in one quantity result in the change in other quantity then 2 quantity are to be in variation.
Inverse
- The more number of men the less time will be taken to finish the work.
- The less number of men the more time will be taken to finish the work.