if 42 persons can do a piece of work in 63 days in how many days will 18 person can do it?
Answers
Answered by
1
=18 days
42 person can do a piece of work in 63 days
so ,1 person can do a piece of work in 3/2 days
so,18 person can do a piece of work in 18 days
42 person can do a piece of work in 63 days
so ,1 person can do a piece of work in 3/2 days
so,18 person can do a piece of work in 18 days