Math, asked by jaatni26, 7 months ago

If 45 men can do a piece of work in 49 days, in how many days will 35 men do it?​

Answers

Answered by rahulerramuri
13

Answer:

35 men can do it in 38 days

Step-by-step explanation:

Number of men = 45      Days=49

Number of men = 35       Days=?

Cross multilpy

35*49=1715

1715/45=38

Answered by SanskariDevil
3

Step-by-step explanation:

above answer is correct

mark above as brainlist answer