If 45 men can do a piece work in the 49 day. In how many days will 35 men do it?

Answers

Answered by Rohit57RA
21

Answer :-

 \large \bold{Given \: That}

No. of Men = 45 men

No. of Days = 49 days

If, No. of Men = 35 men

 \large \bold{To \: Find}

Find the No. of Days.

 \large \bold{Solution}

No. of Men = 45 | 35

No. of days = 49 | ?

It is the Case of Inverse Variation.

Therefore,

Let the No. of Days be 'x'.

45 \:  \times  \: 49 \:  \:  =  \:  \: 35x \\   \frac{45 \times49 }{35 \: }  \:  \:  =  \: x \\  x \:  \:  =  \:  \: 63 \: days