If 45 men do a work in 13 Days. How does 39 men complete task in how many days
Answers
Answered by
0
Answer:
15 day
Step-by-step explanation:
let one man do one work in 1 day
work done by 45 men in 13 days = 45*13
total work = 45*13
work done by 39 men = total work / men
= 45*13/39 = 15 days